Council Meeting/Documents/COUNCIL REPORT: Chilco Trails Zones 3 and 4 – Award of RFP
Staff Report

COUNCIL REPORT: Chilco Trails Zones 3 and 4 – Award of RFP

May 1, 2018Pages 47–482 sections

Recommendation to award a construction contract to Western Watershed Designs Inc. for trail network expansion.

8.1.d Chilco Trails Zones 3 and 4 - Award of RFP
April 27, 2018$94,500.00 total costWestern Watershed Designs Inc.

TOWN OF VIEW ROYAL COUNCIL REPORT

TO: Council
DATE: April 27, 2018
FROM: Kim Anema, CAO
MEETING DATE: May 1, 2018

Page 47–48

Chilco Trails Zones 3 and 4 – Award of RFP

RECOMMENDATION:

THAT Western Watershed Designs Inc. be awarded the contract to construct Chilco Trails Zones 3 and 4 for a total cost of $94,500 including GST.

PURPOSE OF REPORT:

To award the contract for the construction of Zones 3 and 4 of the Chilco Trails network (see attached map).

TIME CRITICAL:

Funds are budgeted for the 2018 budget year and construction season is at hand.

DIRECTOR OF DEVELOPMENT SERVICES’ COMMENTS:

I concur with the recommendation.

BACKGROUND:

Council approved the Chilco Trail Network Design in May 2012. Since that time additional contributions from the developer have facilitated construction of the proposed trail system.

In 2014 a construction program for the development of Zones 1 and 2, inclusive of dog bag dispensers and an observation platform, was completed.

An RFP for this particular area was initially issued in January 2018. The single response did not meet the needs of the Town. The RFP was re-issued in March 15, 2018 with an increased scope of work.

PROJECT INFORMATION:

The current RFP closed April 18, 2018. Two companies submitted responses to the RFP. The following prices were submitted. including tax:

Company Price (including tax) Evaluation
Western Watershed Designs Inc. $94,500.00 Project Evaluation 90 points
Richwood Contracting Ltd. $96,511.14 Project Evaluation 71 points

The criteria used to evaluate the proposals were: Relevant Experience (20 points); References (10 Points); Environmental Criteria (10 points); Price (40 points) and Work Program (20 points). Western Watershed Designs Inc. was also the successful contractor in the development of Zones 1 and 2.

Western Watershed Designs Inc. have indicated a construction schedule of 24 days duration. Both zones would be constructed at the same time.

The Western Watershed Designs Inc. proposal recognizes the fragility of the ecosystem in this area and have factored this into their proposal. They have recommended some invasive species (Scotch Broom) be removed to encourage growth of riparian species.

Staff will send a notice to parcels in Thetis Vale indicating that trail construction is to begin imminently and requesting that people refrain from using the trails until construction is complete.

BUDGET IMPLICATIONS:

The proposal is under the estimated budget.

ALTERNATIVES TO STAFF RECOMMENDATION:

If Council does not wish to award the contract for trail construction, an alternative recommendation would be to table the report and to provide direction to staff.

RECOMMENDATION:

THAT Western Watershed Designs Inc. be awarded the contract to construct Chilco Trails Zones 3 and 4 for a total cost of $94,500 including GST.

SUBMITTED BY: Kim Anema, Chief Administrative Office

Page 47–48