Covenant CA8718173GeneralActiveFollow Matter

Amendment to 9 Erskine Lane Covenant

First seen: October 17, 2023
Last seen: October 17, 2023

Lifecycle Timeline

October 17, 2023Council
Full Recording

Request to Amend Covenant for Erskine Lane/Watkiss Way Roundabout - Further Information

"Ivan Leung presented the technical challenges that made a roundabout unfeasible, including property encroachment and the necessity for significant retaining walls. Council members Rogers and Lemon questioned why these issues were only appearing now and inquired about the potential for dedicated turn lanes and the cost differences. The applicant's engineer, Andy Kading, stated that current traffic volumes could be handled by a single lane, but space exists for future turn lanes if needed. Public speakers and correspondence heavily favored the signalized intersection to prevent the removal of mature trees and ensure better control over pedestrian crossings."
Staff TOWN OF VIEW ROYAL PUBLIC HEARING REPORT: REQUEST TO AMEND COVENANT FOR ERSKINE LANE / WATKISS WAY ROUNDABOUT – FURTHER INFORMATIONStaff TOWN OF VIEW ROYAL PLANNING, DEVELOPMENT AND ENGAGEMENT REPORT: REQUEST TO AMEND COVENANT FOR ERSKINE LANE / WATKISS WAY ROUNDABOUTOther219 COVENANT – DEVELOPMENT AGREEMENT CA8718173CorresLetter of Request: Amendment to Covenant CA8718173 – Development AgreementOtherWATT MEMORANDUM: Watkiss Way and Erskine Lane RoundaboutOtherGeotechnical Assessment: Proposed Roundabout – Existing Retaining Wall ModificationsOther9 ERSKINE LANE Traffic Impact AssessmentOtherAPPENDIX A – SITE PLANOtherAPPENDIX B – SYNCHRO BACKGROUNDOtherAPPENDIX C – SYNCHRO REPORTSOtherSIGNALIZED INTERSECTION LANE DESIGN - WATKISS WAY / ERSKINE LANEOtherTIA Addendum No. 1 – Helmcken Rd. / Watkiss Way IntersectionOtherOpen House Summary: Intersection Improvement Options at Erskine Lane and Watkiss WayPresenPresentation: COVENANT AMENDMENT REQUEST – 9 ERSKINE LANECorresEmail from Carole Trudeau regarding traffic control proposal/Ernskine LaneCorresEmail from Don Denton regarding Blueprint housing project and trafficCorresEmail from Kathleen Gilbert regarding roundabout at ErskineCorresEmail from Glenda Balkan regarding West Urban Development on Erskine LaneCorresEmail from Michael Faulkner regarding Watkiss Way and Erskine LaneCorresEmail from Chris & Nancy Stewart regarding covenant amendment requestCorresEmail from Nicolas Denux regarding public hearing for 9 Erskine LaneCorresEmail from The Shergolds regarding proposed traffic lights projectCorresEmail from Andrew Engelhardt regarding traffic signals at Watkiss and Stoneridge DrCorresEmail from David Kury regarding recommendation to amend Covenant CA8718173CorresEmail from Jessica Arnet regarding CRD Comments - 9 Erskine RoadFormCRD Staff Referral Response FormCorresEmail from Doug Wilson regarding Watkiss Roundabout
Formal MotionPassed
"THAT the report dated October 11, 2023 from the Director of Engineering and Senior Planner titled “Request to Amend Covenant for Erskine Lane/Watkiss Way Roundabout – Further Information” be received for information."
Moved by: John Rogers
Seconded by: Don Brown
Sid Tobias
Don Brown
Damian Kowalewich
Gery Lemon
Ron Mattson
John Rogers